With our remarkable services & solutions, Enriched your business
| SL. No | Project/job site (50) | Country (50) | State, if in India | Client/Lead Contractor (50) | Wo Value (rs. lakhs) | Duration of job in months | Status of Job |
|---|---|---|---|---|---|---|---|
| 1 | GETCO-ARC WORK | INDIA | GUJARAT | GLOBE ECO and JV WITH NISHI TRAFOCARE | APPROX 400 LACKS | 2 YEARS | RUNNING |
| 2 | GETCO | INDIA | GUJARAT | ATLANTA ELECTRICALS | 40 LACKS | 1 YEAR | RUNNING |
| 3 | GETCO | INDIA | GUJARAT | CGL | 7 LACKS | 2 MONTHS | RUNNING |
| 4 | GETCO | INDIA | GUJARAT | T & R | APPROX 100 LACKS | 3 YEARS | COMPLETED |
| 5 | GETCO | INDIA | GUJARAT | CGL | 12 LACKS | 2 MONTHS | COMPLETED |
| 6 | GETCO-NADIAD | INDIA | GUJARAT | GETCO | 32.97 LACKS | 1 YEAR | COMPLETED |
| 7 | GETCO-NADIAD | INDIA | GUJARAT | GETCO | 16.86 LACKS | 1 YEAR | COMPLETED |
| 8 | GETCO-BHARUCH | INDIA | GUJARAT | GETCO | 6.78 LACKS | 20 DAYS | COMPLETED |
| 9 | Institute for Plasma Research-Gandhinagar | INDIA | GUJARAT | GETCO | 10 LACKS | 2 MONTHS | Running |
| SR NO | RATING | QUANTITY |
|---|---|---|
| 1 | 500MVA, 400/220/33 KV | 1 |
| 2 | 125MVAR 420KV SHUNT REACTOR | 2 |
| 3 | 63MVAR 420KV SHUNT REACTOR | 1 |
| 4 | 315MVA, 400/220/33 KV | 1 |
| 5 | 150MVA, 220/66KV | 1 |
| 6 | 100MVA, 220/66KV | 38 |
| 7 | 100MVA, 220/132/11 KV | 4 |
| 8 | 50MVA,132/66 KV | 8 |
| 9 | 25MVA, 132/11 KV | 4 |
| 10 | 10, 15, 20 MVA, 66/11.5KV | 150 |